Americold
Dunkirk, New York
- 136,000 sf -20°F freezer with 50 ft clear height
- 480,000 gallon fire protection water tank
- Temperature-Controlled Facility
- 20-acre site
- 11,000 sf repack dock
- 25,000 pallet positions
- 34 dock positions
Construction of a 181,000 sf temperature-controlled facility for Americold in Dunkirk, NY. The building sits on a 20-acre site that required wetland delineation and features a two-story office/support space area and a 136,000 sf -20F freezer with 50 ft clear height. The project was designed to be capable of adding a rail dock at the rear of the building. Additionally, the facility boasts a 480,000 gallon fire protection water storage tank and associated diesel fire pump.
Building for the Future & LEED
This fast-tracked project was designed to accommodate a future rail dock and included a -20°F section with processing in the dock area. Harsh winter weather and deep snow added to the construction challenges. The LEED Silver certification was achieved with the help of Power Cold+Food Group and ALTA Refrigeration, who collaborated on the energy-efficient design. Unique features also included wetland delineation and a design shift that relocated the pump house into the main building for efficiency and environmental compliance.
Self-Perform
Our self-perform group completed the installation of insulated metal wall panels, floor insulation and miscellaneous carpentry items, as well as refrigerated doors for the facility.